Capacity Curtailment on the HU-AT border for delivery period 07-09-2024
1. TSO(s):
APG
2. Identification of affected Long Term Transmission Rights:
HU-AT
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Affected volume in MW / hour for each concerned period:
07-09-2024 00:00 - 01:00 249 MW
07-09-2024 01:00 - 02:00 249 MW
07-09-2024 02:00 - 03:00 249 MW
07-09-2024 03:00 - 04:00 249 MW
07-09-2024 04:00 - 05:00 249 MW
07-09-2024 05:00 - 06:00 249 MW
07-09-2024 06:00 - 07:00 249 MW
07-09-2024 07:00 - 08:00 249 MW
07-09-2024 08:00 - 09:00 249 MW
07-09-2024 09:00 - 10:00 249 MW
07-09-2024 10:00 - 11:00 249 MW
07-09-2024 11:00 - 12:00 249 MW
07-09-2024 12:00 - 13:00 249 MW
07-09-2024 13:00 - 14:00 249 MW
07-09-2024 14:00 - 15:00 249 MW
07-09-2024 15:00 - 16:00 249 MW
07-09-2024 16:00 - 17:00 249 MW
07-09-2024 17:00 - 18:00 249 MW
07-09-2024 18:00 - 19:00 249 MW
07-09-2024 19:00 - 20:00 249 MW
07-09-2024 20:00 - 21:00 249 MW
07-09-2024 21:00 - 22:00 249 MW
07-09-2024 22:00 - 23:00 249 MW
07-09-2024 23:00 - 24:00 249 MW
5. Amount of LTTR remaining after curtailment:
07-09-2024 00:00 - 01:00 0 MW
07-09-2024 01:00 - 02:00 0 MW
07-09-2024 02:00 - 03:00 0 MW
07-09-2024 03:00 - 04:00 0 MW
07-09-2024 04:00 - 05:00 0 MW
07-09-2024 05:00 - 06:00 0 MW
07-09-2024 06:00 - 07:00 0 MW
07-09-2024 07:00 - 08:00 0 MW
07-09-2024 08:00 - 09:00 0 MW
07-09-2024 09:00 - 10:00 0 MW
07-09-2024 10:00 - 11:00 0 MW
07-09-2024 11:00 - 12:00 0 MW
07-09-2024 12:00 - 13:00 0 MW
07-09-2024 13:00 - 14:00 0 MW
07-09-2024 14:00 - 15:00 0 MW
07-09-2024 15:00 - 16:00 0 MW
07-09-2024 16:00 - 17:00 0 MW
07-09-2024 17:00 - 18:00 0 MW
07-09-2024 18:00 - 19:00 0 MW
07-09-2024 19:00 - 20:00 0 MW
07-09-2024 20:00 - 21:00 0 MW
07-09-2024 21:00 - 22:00 0 MW
07-09-2024 22:00 - 23:00 0 MW
07-09-2024 23:00 - 24:00 0 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment:
Expected violation of operational security limits of physical transmission assets.
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)?
During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation.