Capacity Curtailment on the HU-AT border for delivery period 12-01-2025
1. TSO(s)*:
APG
2. Identification of affected Long Term Transmission Rights:
HU-AT
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Affected volume in MW / hour for each concerned period:
12-01-2025 11:00 - 12:00 339 MW
12-01-2025 12:00 - 13:00 339 MW
12-01-2025 13:00 - 14:00 339 MW
5. Amount of LTTR remaining after curtailment:
12-01-2025 11:00 - 12:00 242 MW
12-01-2025 12:00 - 13:00 238 MW
12-01-2025 13:00 - 14:00 267 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:
Expected violation of operational security limits of physical transmission assets.
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?
During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation.