Capacity Curtailment on the HU-AT border for delivery period 15-02-2026

Published:

1. TSO(s)*:

APG

2. Identification of affected Long Term Transmission Rights:

HU-AT

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

15-02-2026 00:00 - 01:00 339 MW

15-02-2026 01:00 - 02:00 339 MW

15-02-2026 02:00 - 03:00 339 MW

15-02-2026 03:00 - 04:00 339 MW

15-02-2026 04:00 - 05:00 339 MW

15-02-2026 05:00 - 06:00 339 MW

15-02-2026 06:00 - 07:00 339 MW

15-02-2026 07:00 - 08:00 339 MW

15-02-2026 08:00 - 09:00 339 MW

15-02-2026 09:00 - 10:00 339 MW

5. Amount of LTTR remaining after curtailment:

15-02-2026 00:00 - 01:00 201 MW

15-02-2026 01:00 - 02:00 197 MW

15-02-2026 02:00 - 03:00 177 MW

15-02-2026 03:00 - 04:00 164 MW

15-02-2026 04:00 - 05:00 164 MW

15-02-2026 05:00 - 06:00 177 MW

15-02-2026 06:00 - 07:00 215 MW

15-02-2026 07:00 - 08:00 161 MW

15-02-2026 08:00 - 09:00 165 MW

15-02-2026 09:00 - 10:00 227 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:

Expected violation of operational security limits of physical transmission assets.

 

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?

During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation.