Capacity Curtailment on the HU-AT border for delivery period 26-05-2025
1. TSO(s)*:
APG
2. Identification of affected Long Term Transmission Rights:
HU-AT
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Affected volume in MW / hour for each concerned period:
26-05-2025 06:00 - 07:00 294 MW
26-05-2025 07:00 - 08:00 294 MW
26-05-2025 08:00 - 09:00 294 MW
26-05-2025 09:00 - 10:00 294 MW
26-05-2025 10:00 - 11:00 294 MW
26-05-2025 11:00 - 12:00 294 MW
26-05-2025 12:00 - 13:00 294 MW
26-05-2025 13:00 - 14:00 294 MW
26-05-2025 14:00 - 15:00 294 MW
26-05-2025 15:00 - 16:00 294 MW
26-05-2025 16:00 - 17:00 294 MW
26-05-2025 17:00 - 18:00 294 MW
5. Amount of LTTR remaining after curtailment:
26-05-2025 06:00 - 07:00 236 MW
26-05-2025 07:00 - 08:00 236 MW
26-05-2025 08:00 - 09:00 236 MW
26-05-2025 09:00 - 10:00 236 MW
26-05-2025 10:00 - 11:00 236 MW
26-05-2025 11:00 - 12:00 236 MW
26-05-2025 12:00 - 13:00 236 MW
26-05-2025 13:00 - 14:00 236 MW
26-05-2025 14:00 - 15:00 236 MW
26-05-2025 15:00 - 16:00 236 MW
26-05-2025 16:00 - 17:00 236 MW
26-05-2025 17:00 - 18:00 236 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:
Expected violation of operational security limits of physical transmission assets.
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?
During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation.