Capacity Curtailment on the HU-AT border for delivery period 30-06-2025
1. TSO(s)*:
APG
2. Identification of affected Long Term Transmission Rights:
HU-AT
3. Triggering event:
Curtailment due to Force Majeure
4. Affected volume in MW / hour for each concerned period:
30-06-2025 00:00 - 01:00 294 MW
30-06-2025 01:00 - 02:00 294 MW
30-06-2025 02:00 - 03:00 294 MW
30-06-2025 03:00 - 04:00 294 MW
30-06-2025 04:00 - 05:00 294 MW
30-06-2025 05:00 - 06:00 294 MW
30-06-2025 16:00 - 17:00 294 MW
30-06-2025 17:00 - 18:00 294 MW
30-06-2025 23:00 - 24:00 294 MW
5. Amount of LTTR remaining after curtailment:
30-06-2025 00:00 - 01:00 202 MW
30-06-2025 01:00 - 02:00 197 MW
30-06-2025 02:00 - 03:00 200 MW
30-06-2025 03:00 - 04:00 235 MW
30-06-2025 04:00 - 05:00 202 MW
30-06-2025 05:00 - 06:00 233 MW
30-06-2025 16:00 - 17:00 246 MW
30-06-2025 17:00 - 18:00 246 MW
30-06-2025 23:00 - 24:00 256 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:
Expected violation of operational security limits of physical transmission assets.
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?
During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation.