Capacity Curtailment on the IF1 border for delivery 23-08-2023 to 31-08-2023

Published:

1. TSO(s)*:

National Grid Interconnectors Limited (NGIC) and RTE EDF Transport S.A. (RTE)

 

2. Identification of affected Long Term Transmission Rights:

IF1-FR-GB and IF1-GB-FR

 

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

 

4. Affected volume in MW / hour for each concerned period:

From
23-08-2023 08:00 - 09:00 1300 MW

To
31-08-2023 23:00 - 24:00 1300 MW

 

5. Amount of LTTR remaining after curtailment:

From

23-08-2023 08:00 - 09:00 964 MW

To

31-08-2023 23:00 - 24:00 964 MW

 

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:

Thermal Limits

 

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?

Capacity limitation due to planned maintenance