Capacity Curtailment on the IF1-FR-GB border for delivery 26-03-2024
1. TSO(s)*:
National Grid Interconnectors Limited (NGIC) and RTE EDF Transport S.A. (RTE)
2. Identification of affected Long Term Transmission Rights:
IF1-FR-GB
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Affected volume in MW / hour for each concerned period:
26-03-2024 07:00 - 08:00 1299 MW
26-03-2024 08:00 - 09:00 1299 MW
26-03-2024 09:00 - 10:00 1299 MW
26-03-2024 10:00 - 11:00 1299 MW
26-03-2024 11:00 - 12:00 1299 MW
26-03-2024 12:00 - 13:00 1299 MW
26-03-2024 13:00 - 14:00 1299 MW
26-03-2024 14:00 - 15:00 1299 MW
26-03-2024 15:00 - 16:00 1299 MW
26-03-2024 16:00 - 17:00 1299 MW
26-03-2024 17:00 - 18:00 1299 MW
5. Amount of LTTR remaining after curtailment:
26-03-2024 07:00 - 08:00 953 MW
26-03-2024 08:00 - 09:00 953 MW
26-03-2024 09:00 - 10:00 953 MW
26-03-2024 10:00 - 11:00 953 MW
26-03-2024 11:00 - 12:00 953 MW
26-03-2024 12:00 - 13:00 953 MW
26-03-2024 13:00 - 14:00 953 MW
26-03-2024 14:00 - 15:00 953 MW
26-03-2024 15:00 - 16:00 953 MW
26-03-2024 16:00 - 17:00 953 MW
26-03-2024 17:00 - 18:00 953 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:
Thermal Limits
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?
Capacity limitation due to planned maintenance.