Capacity Curtailment on the IF1-FR-GB border for delivery period 16-03-2026
1. TSO(s)*:
National Grid Interconnectors Limited (NGIC) and RTE EDF Transport S.A. (RTE)
2. Identification of affected Long Term Transmission Rights:
IF1-FR-GB
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Affected volume in MW / hour for each concerned period:
16-03-2026 15:00 - 16:00 1500 MW
16-03-2026 16:00 - 17:00 1500 MW
5. Amount of LTTR remaining after curtailment:
16-03-2026 15:00 - 16:00 966 MW
16-03-2026 16:00 - 17:00 966 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:
Thermal Limits
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?
Capacity limitation due to planned maintenance