Capacity Curtailment on the IF1 FR <>GB border for delivery day 10/06/2021

Published:

FR>GB

  1. TSO(s) *:

National Grid Interconnectors Limited (NGIC) and RTE EDF Transport S.A. (RTE)

  1. Identification of affected Long Term Transmission Rights

IFA FR>GB

  1. Triggering event :

☒Curtailment to ensure operation remains within Operational Security Limits

☐Curtailment due to Force Majeure

☐Curtailment due to emergency situation

  1. Affected volume in MW / hour for each concerned period :

10/06/2021

00:00 - 01:00        1699

01:00 - 02:00        1699

02:00 - 03:00        1699

03:00 - 04:00        1699

04:00 - 05:00        1699

05:00 - 06:00        1699

06:00 - 07:00        1699

07:00 - 08:00        1699

08:00 - 09:00        1699

09:00 - 10:00        1699

10:00 - 11:00        1699

11:00 - 12:00        1699

12:00 - 13:00        1699

13:00 - 14:00        1699

14:00 - 15:00        1699

15:00 - 16:00        1699

16:00 - 17:00        1699

17:00 - 18:00        1699

18:00 - 19:00        1699

19:00 - 20:00        1699

20:00 - 21:00        1699

21:00 - 22:00        1699

22:00 - 23:00        1699

23:00 - 00:00        1699

  1. Amount of LTTR remaining after curtailment :

10/06/2021

00:00 - 01:00        1500

01:00 - 02:00        1500

02:00 - 03:00        1500

03:00 - 04:00        1500

04:00 - 05:00        1500

05:00 - 06:00        1500

06:00 - 07:00        1500

07:00 - 08:00        1500

08:00 - 09:00        1500

09:00 - 10:00        1500

10:00 - 11:00        1500

11:00 - 12:00        1500

12:00 - 13:00        1500

13:00 - 14:00        1500

14:00 - 15:00        1500

15:00 - 16:00        1500

16:00 - 17:00        1500

17:00 - 18:00        1500

18:00 - 19:00        1500

19:00 - 20:00        1500

20:00 - 21:00        1500

21:00 - 22:00        1500

22:00 - 23:00        1500

23:00 - 00:00        1500

  1. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:

Thermal Limits

  1. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?

Capacity limitation due to unplanned maintenance

GB > FR

  1. TSO(s) *:

National Grid Interconnectors Limited (NGIC) and RTE EDF Transport S.A. (RTE)

  1. Identification of affected Long Term Transmission Rights

IFA GB>FR

  1. Triggering event :

☒Curtailment to ensure operation remains within Operational Security Limits

☐Curtailment due to Force Majeure

☐Curtailment due to emergency situation

  1. Affected volume in MW / hour for each concerned period:

10/06/2021

00:00 - 01:00        1694

01:00 - 02:00        1694

02:00 - 03:00        1694

03:00 - 04:00        1694

04:00 - 05:00        1694

05:00 - 06:00        1694

06:00 - 07:00        1694

07:00 - 08:00        1694

08:00 - 09:00        1694

09:00 - 10:00        1694

10:00 - 11:00        1694

11:00 - 12:00        1694

12:00 - 13:00        1694

13:00 - 14:00        1694

14:00 - 15:00        1694

15:00 - 16:00        1694

16:00 - 17:00        1694

17:00 - 18:00        1694

18:00 - 19:00        1694

19:00 - 20:00        1694

20:00 - 21:00        1694

21:00 - 22:00        1694

22:00 - 23:00        1694

23:00 - 00:00        1694

  1. Amount of LTTR remaining after curtailment:

10/06/2021

00:00 - 01:00        1500

01:00 - 02:00        1500

02:00 - 03:00        1500

03:00 - 04:00        1500

04:00 - 05:00        1500

05:00 - 06:00        1500

06:00 - 07:00        1500

07:00 - 08:00        1500

08:00 - 09:00        1500

09:00 - 10:00        1500

10:00 - 11:00        1500

11:00 - 12:00        1500

12:00 - 13:00        1500

13:00 - 14:00        1500

14:00 - 15:00        1500

15:00 - 16:00        1500

16:00 - 17:00        1500

17:00 - 18:00        1500

18:00 - 19:00        1500

19:00 - 20:00        1500

20:00 - 21:00        1500

21:00 - 22:00        1500

22:00 - 23:00        1500

23:00 - 00:00        1500

  1. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:

Thermal Limits

  1. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?

Capacity limitation due to unplanned maintenance