Capacity Curtailment on the IF1-FR-GB <>IF1-GB-FR border for delivery period 04-05-2025 00:00 - 08-05-2025 00:00

Published:

1. TSO(s)*:

National Grid Interconnectors Limited (NGIC) and RTE EDF Transport S.A. (RTE)

 

2. Identification of affected Long Term Transmission Rights:

 IF1-FR-GB <>IF1-GB-FR

 

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

 

4. Affected volume in MW / hour for each concerned period:

 00:00 - 01:00 1950 MW 

 01:00 - 02:00 1950 MW 

 02:00 - 03:00 1950 MW 

 03:00 - 04:00 1950 MW 

 04:00 - 05:00 1950 MW 

 05:00 - 06:00 1950 MW 

 06:00 - 07:00 1950 MW 

 07:00 - 08:00 1950 MW 

 08:00 - 09:00 1950 MW 

 09:00 - 10:00 1950 MW 

 10:00 - 11:00 1950 MW 

 11:00 - 12:00 1950 MW 

 12:00 - 13:00 1950 MW 

 13:00 - 14:00 1950 MW 

 14:00 - 15:00 1950 MW 

 15:00 - 16:00 1950 MW 

 16:00 - 17:00 1950 MW 

 17:00 - 18:00 1950 MW 

 18:00 - 19:00 1950 MW 

 19:00 - 20:00 1950 MW 

 20:00 - 21:00 1950 MW 

 21:00 - 22:00 1950 MW 

 22:00 - 23:00 1950 MW 

 23:00 - 24:00 1950 MW

 

5. Amount of LTTR remaining after curtailment:

 00:00 - 01:00 1470 MW 

 01:00 - 02:00 1470 MW 

 02:00 - 03:00 1470 MW 

 03:00 - 04:00 1470 MW 

 04:00 - 05:00 1470 MW 

 05:00 - 06:00 1470 MW 

 06:00 - 07:00 1470 MW 

 07:00 - 08:00 1470 MW 

 08:00 - 09:00 1470 MW 

 09:00 - 10:00 1470 MW 

 10:00 - 11:00 1470 MW 

 11:00 - 12:00 1470 MW 

 12:00 - 13:00 1470 MW 

 13:00 - 14:00 1470 MW 

 14:00 - 15:00 1470 MW 

 15:00 - 16:00 1470 MW 

 16:00 - 17:00 1470 MW 

 17:00 - 18:00 1470 MW 

 18:00 - 19:00 1470 MW 

 19:00 - 20:00 1470 MW 

 20:00 - 21:00 1470 MW 

 21:00 - 22:00 1470 MW 

 22:00 - 23:00 1470 MW 

 23:00 - 24:00 1470 MW

 

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*: 

Thermal Limits

 

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*? 

Capacity limitation due to unplanned maintenance