Capacity Curtailment on the IF1-FR<>GB border for delivery 27-02-2023
Dear Market Participants,
Please see below information on curtailment on 27-02-2023 on IFA1.
FR>GB
- TSO(s) *:
National Grid Interconnectors Limited (NGIC) and RTE EDF Transport S.A. (RTE)
- Identification of affected Long Term Transmission Rights
IFA FR>GB
- Triggering event :
|
☒Curtailment to ensure operation remains within Operational Security Limits |
|
☐Curtailment due to Force Majeure |
|
☐Curtailment due to emergency situation |
- Affected volume in MW / hour for each concerned period :
27/02/2023
07:00 - 08:00 1400
…
21:00 - 22:00 1400
- Amount of LTTR remaining after curtailment :
27/02/2023
07:00 - 08:00 1000
…
21:00 - 22:00 1000
- Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:
Thermal Limits
- Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?
Capacity limitation due to unplanned maintenance
GB > FR
- TSO(s) *:
National Grid Interconnectors Limited (NGIC) and RTE EDF Transport S.A. (RTE)
- Identification of affected Long Term Transmission Rights
IFA GB>FR
- Triggering event :
|
☒Curtailment to ensure operation remains within Operational Security Limits |
|
☐Curtailment due to Force Majeure |
|
☐Curtailment due to emergency situation |
- Affected volume in MW / hour for each concerned period:
27/02/2023
07:00 - 08:00 1399
…
21:00 - 22:00 1399
- Amount of LTTR remaining after curtailment:
27/02/2023
07:00 - 08:00 1000
…
21:00 - 22:00 1000
- Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:
Thermal Limits
- Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?
Capacity limitation due to unplanned maintenance