Capacity Curtailment on the IF1-GB-FR border for delivery period 28-02-2025

Published:

1. TSO(s)*:

RNP

2. Identification of affected Long Term Transmission Rights:

IF1-GB-FR

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

28-02-2025 08:00 - 09:00 1400 MW

28-02-2025 16:00 - 17:00 1400 MW

5. Amount of LTTR remaining after curtailment:

28-02-2025 08:00 - 09:00 961 MW

28-02-2025 16:00 - 17:00 961 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?

*According to section 57.3 of the EU HAR, this field can be filled in within 24 hours after the initial publication