Capacity Curtailment on the IF1-GB-FR border for delivery period 07-07-2025
1. TSO(s)*:
RNP
2. Identification of affected Long Term Transmission Rights:
IF1-GB-FR
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Affected volume in MW / hour for each concerned period:
07-07-2025 00:00 - 01:00 1900 MW
07-07-2025 01:00 - 02:00 1900 MW
07-07-2025 02:00 - 03:00 1900 MW
07-07-2025 03:00 - 04:00 1900 MW
07-07-2025 04:00 - 05:00 1900 MW
07-07-2025 05:00 - 06:00 1900 MW
07-07-2025 06:00 - 07:00 1900 MW
07-07-2025 07:00 - 08:00 1900 MW
07-07-2025 08:00 - 09:00 1900 MW
07-07-2025 09:00 - 10:00 1900 MW
07-07-2025 10:00 - 11:00 1900 MW
07-07-2025 11:00 - 12:00 1900 MW
5. Amount of LTTR remaining after curtailment:
07-07-2025 00:00 - 01:00 1426 MW
07-07-2025 01:00 - 02:00 1426 MW
07-07-2025 02:00 - 03:00 1426 MW
07-07-2025 03:00 - 04:00 1426 MW
07-07-2025 04:00 - 05:00 1426 MW
07-07-2025 05:00 - 06:00 1426 MW
07-07-2025 06:00 - 07:00 1426 MW
07-07-2025 07:00 - 08:00 1426 MW
07-07-2025 08:00 - 09:00 1426 MW
07-07-2025 09:00 - 10:00 1426 MW
07-07-2025 10:00 - 11:00 1426 MW
07-07-2025 11:00 - 12:00 1426 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:
Thermal Limits
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?
Capacity limitation due to unplanned maintenance