Capacity Curtailment on the IF1-GB<>FR border for delivery day 10/03/2022 – 15/03/2022

Published:

FR>GB

  1. TSO(s) *:

National Grid Interconnectors Limited (NGIC) and RTE EDF Transport S.A. (RTE)

  1. Identification of affected Long Term Transmission Rights

IFA FR>GB

  1. Triggering event :

☒Curtailment to ensure operation remains within Operational Security Limits

☐Curtailment due to Force Majeure

☐Curtailment due to emergency situation

  1. Affected volume in MW / hour for each concerned period :

10/03/2022 to 15/03/2022

00:00 - 01:00        1000

01:00 - 02:00        1000

02:00 - 03:00        1000

03:00 - 04:00        1000

04:00 - 05:00        1000

05:00 - 06:00        1000

06:00 - 07:00        1000

07:00 - 08:00        1000

08:00 - 09:00        1000

09:00 - 10:00        1000

10:00 - 11:00        1000

11:00 - 12:00        1000

12:00 - 13:00        1000

13:00 - 14:00        1000

14:00 - 15:00        1000

15:00 - 16:00        1000

16:00 - 17:00        1000

17:00 - 18:00        1000

18:00 - 19:00        1000

19:00 - 20:00        1000

20:00 - 21:00        1000

21:00 - 22:00        1000

22:00 - 23:00        1000

23:00 - 00:00        1000

  1. Amount of LTTR remaining after curtailment :

10/03/2022 to 15/03/2022

00:00 - 01:00        500

01:00 - 02:00        500

02:00 - 03:00        500

03:00 - 04:00        500

04:00 - 05:00        500

05:00 - 06:00        500

06:00 - 07:00        500

07:00 - 08:00        500

08:00 - 09:00        500

09:00 - 10:00        500

10:00 - 11:00        500

11:00 - 12:00        500

12:00 - 13:00        500

13:00 - 14:00        500

14:00 - 15:00        500

15:00 - 16:00        500

16:00 - 17:00        500

17:00 - 18:00        500

18:00 - 19:00        500

19:00 - 20:00        500

20:00 - 21:00        500

21:00 - 22:00        500

22:00 - 23:00        500

23:00 - 00:00        500

  1. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:

Thermal Limits

  1. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?

Capacity limitation due to unplanned maintenance

GB > FR

  1. TSO(s) *:

National Grid Interconnectors Limited (NGIC) and RTE EDF Transport S.A. (RTE)

  1. Identification of affected Long Term Transmission Rights

IFA GB>FR

  1. Triggering event :

☒Curtailment to ensure operation remains within Operational Security Limits

☐Curtailment due to Force Majeure

☐Curtailment due to emergency situation

  1. Affected volume in MW / hour for each concerned period:

10/03/2022 to 15/03/2022

00:00 - 01:00        1000

01:00 - 02:00        1000

02:00 - 03:00        1000

03:00 - 04:00        1000

04:00 - 05:00        1000

05:00 - 06:00        1000

06:00 - 07:00        1000

07:00 - 08:00        1000

08:00 - 09:00        1000

09:00 - 10:00        1000

10:00 - 11:00        1000

11:00 - 12:00        1000

12:00 - 13:00        1000

13:00 - 14:00        1000

14:00 - 15:00        1000

15:00 - 16:00        1000

16:00 - 17:00        1000

17:00 - 18:00        1000

18:00 - 19:00        1000

19:00 - 20:00        1000

20:00 - 21:00        1000

21:00 - 22:00        1000

22:00 - 23:00        1000

23:00 - 00:00        1000

  1. Amount of LTTR remaining after curtailment:

10/03/2022 to 15/03/2022

00:00 - 01:00        500

01:00 - 02:00        500

02:00 - 03:00        500

03:00 - 04:00        500

04:00 - 05:00        500

05:00 - 06:00        500

06:00 - 07:00        500

07:00 - 08:00        500

08:00 - 09:00        500

09:00 - 10:00        500

10:00 - 11:00        500

11:00 - 12:00        500

12:00 - 13:00        500

13:00 - 14:00        500

14:00 - 15:00        500

15:00 - 16:00        500

16:00 - 17:00        500

17:00 - 18:00        500

18:00 - 19:00        500

19:00 - 20:00        500

20:00 - 21:00        500

21:00 - 22:00        500

22:00 - 23:00        500

23:00 - 00:00        500

  1. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:

Thermal Limits

  1. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?

Capacity limitation due to unplanned maintenance