Capacity Curtailment on the IF1-GB<>FR border for delivery days 19/09/22 - 14/10/22
FR>GB
- TSO(s) *:
National Grid Interconnectors Limited (NGIC) and RTE EDF Transport S.A. (RTE)
- Identification of affected Long Term Transmission Rights
IFA FR>GB
- Triggering event :
☒Curtailment to ensure operation remains within Operational Security Limits |
☐Curtailment due to Force Majeure |
☐Curtailment due to emergency situation |
- Affected volume in MW / hour for each concerned period :
19/9/22 00:00 to 30/9/22 23:59 – 850MW
1/10/22 00:00 to 14/10/22 23:59 – 800MW
- Amount of LTTR remaining after curtailment :
19/9/22 00:00 to 14/10/22 23:59 – 0MW
- Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:
Breach of Thermal Limits
- Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?
Asset Maintenance
GB > FR
- TSO(s) *:
National Grid Interconnectors Limited (NGIC) and RTE EDF Transport S.A. (RTE)
- Identification of affected Long Term Transmission Rights
IFA GB>FR
- Triggering event :
☒Curtailment to ensure operation remains within Operational Security Limits |
☐Curtailment due to Force Majeure |
☐Curtailment due to emergency situation |
- Affected volume in MW / hour for each concerned period :
19/9/22 00:00 to 30/9/22 23:59 – 850MW
1/10/22 00:00 to 14/10/22 23:59 – 800MW
- Amount of LTTR remaining after curtailment :
19/9/22 00:00 to 14/10/22 23:59 – 0MW
- Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:
Breach of Thermal Limits
- Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?
Asset Maintenance