Capacity Curtailment on the IF2-FR-GB border for delivery period 28-04-2025

Published:

1. TSO(s)*:

NGIC

2. Identification of affected Long Term Transmission Rights:

IF2-FR-GB

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

28-04-2025 09:00 - 10:00 844 MW

28-04-2025 10:00 - 11:00 844 MW

28-04-2025 11:00 - 12:00 844 MW

28-04-2025 12:00 - 13:00 844 MW

28-04-2025 13:00 - 14:00 844 MW

28-04-2025 14:00 - 15:00 844 MW

28-04-2025 15:00 - 16:00 844 MW

28-04-2025 16:00 - 17:00 844 MW

28-04-2025 17:00 - 18:00 844 MW

28-04-2025 18:00 - 19:00 844 MW

28-04-2025 19:00 - 20:00 844 MW

28-04-2025 20:00 - 21:00 844 MW

28-04-2025 21:00 - 22:00 844 MW

28-04-2025 22:00 - 23:00 844 MW

28-04-2025 23:00 - 24:00 844 MW

5. Amount of LTTR remaining after curtailment:

28-04-2025 09:00 - 10:00 0 MW

28-04-2025 10:00 - 11:00 0 MW

28-04-2025 11:00 - 12:00 0 MW

28-04-2025 12:00 - 13:00 0 MW

28-04-2025 13:00 - 14:00 0 MW

28-04-2025 14:00 - 15:00 0 MW

28-04-2025 15:00 - 16:00 0 MW

28-04-2025 16:00 - 17:00 0 MW

28-04-2025 17:00 - 18:00 0 MW

28-04-2025 18:00 - 19:00 0 MW

28-04-2025 19:00 - 20:00 0 MW

28-04-2025 20:00 - 21:00 0 MW

28-04-2025 21:00 - 22:00 0 MW

28-04-2025 22:00 - 23:00 0 MW

28-04-2025 23:00 - 24:00 0 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:

Thermal Limits

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?

Capacity limitation due to planned maintenance

*According to section 57.3 of the EU HAR, this field can be filled in within 24 hours after the initial publication