Capacity Curtailment on the IF2 ( FR <>GB) border for delivery day 08/11/2022

Published:

Dear Market Participants,

Please find a Long term curtailment below for delivery day  8th November 2022 for IFA2.

FR>GB

  1. TSO(s) *:

National Grid Interconnectors Limited (NGIC) and RTE EDF Transport S.A. (RTE)

  1. Identification of affected Long Term Transmission Rights

IFA2 FR>GB

  1. Triggering event :

☒Curtailment to ensure operation remains within Operational Security Limits

☐Curtailment due to Force Majeure

☐Curtailment due to emergency situation

  1. Affected volume in MW / hour for each concerned period :

08/11/2022

00:00 - 01:00        800

01:00 - 02:00        800

02:00 - 03:00        800

03:00 - 04:00        800

04:00 - 05:00        800

05:00 - 06:00        800

06:00 - 07:00        800

07:00 - 08:00        800

08:00 - 09:00        800

09:00 - 10:00        800

10:00 - 11:00        800

11:00 - 12:00        800

12:00 - 13:00        800

13:00 - 14:00        800

14:00 - 15:00        800

15:00 - 16:00        800

16:00 - 17:00        800

17:00 - 18:00        800

18:00 - 19:00        800

19:00 - 20:00        800

20:00 - 21:00        800

21:00 - 22:00        800

22:00 - 23:00        800

23:00 - 00:00        800

  1. Amount of LTTR remaining after curtailment :

08/11/2022

00:00 - 01:00        800

01:00 - 02:00        800

02:00 - 03:00        800

03:00 - 04:00        800

04:00 - 05:00        800

05:00 - 06:00        800

06:00 - 07:00        800

07:00 - 08:00        800

08:00 - 09:00        800

09:00 - 10:00        800

10:00 - 11:00        0

11:00 - 12:00        0

12:00 - 13:00        0

13:00 - 14:00        0

14:00 - 15:00        0

15:00 - 16:00        0

16:00 - 17:00        0

17:00 - 18:00        0

18:00 - 19:00        0

19:00 - 20:00        0

20:00 - 21:00        800

21:00 - 22:00        800

22:00 - 23:00        800

23:00 - 00:00        800

  1. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:

Thermal Limits

  1. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?

Capacity limitation due to planned maintenance

GB > FR

  1. TSO(s) *:

National Grid Interconnectors Limited (NGIC) and RTE EDF Transport S.A. (RTE)

  1. Identification of affected Long Term Transmission Rights

IFA2 GB>FR

  1. Triggering event :

☒Curtailment to ensure operation remains within Operational Security Limits

☐Curtailment due to Force Majeure

☐Curtailment due to emergency situation

  1. Affected volume in MW / hour for each concerned period:

08/11/2022

00:00 - 01:00        800

01:00 - 02:00        800

02:00 - 03:00        800

03:00 - 04:00        800

04:00 - 05:00        800

05:00 - 06:00        800

06:00 - 07:00        800

07:00 - 08:00        800

08:00 - 09:00        800

09:00 - 10:00        800

10:00 - 11:00        800

11:00 - 12:00        800

12:00 - 13:00        800

13:00 - 14:00        800

14:00 - 15:00        800

15:00 - 16:00        800

16:00 - 17:00        800

17:00 - 18:00        800

18:00 - 19:00        800

19:00 - 20:00        800

20:00 - 21:00        800

21:00 - 22:00        800

22:00 - 23:00        800

23:00 - 00:00        800

  1. Amount of LTTR remaining after curtailment:

08/11/2022

00:00 - 01:00        800

01:00 - 02:00        800

02:00 - 03:00        800

03:00 - 04:00        800

04:00 - 05:00        800

05:00 - 06:00        800

06:00 - 07:00        800

07:00 - 08:00        800

08:00 - 09:00        800

09:00 - 10:00        800

10:00 - 11:00        0

11:00 - 12:00        0

12:00 - 13:00        0

13:00 - 14:00        0

14:00 - 15:00        0

15:00 - 16:00        0

16:00 - 17:00        0

17:00 - 18:00        0

18:00 - 19:00        0

19:00 - 20:00        0

20:00 - 21:00        800

21:00 - 22:00        800

22:00 - 23:00        800

23:00 - 00:00        800

  1. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:

Thermal Limits

  1. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?

Capacity limitation due to planned maintenance

Best regards,

JAO Operations