Capacity Curtailment on IFA1 border for delivery month DECEMBER 2021

Published:

FR>GB

  1. TSO(s) *:

National Grid Interconnectors Limited (NGIC) and RTE EDF Transport S.A. (RTE)

  1. Identification of affected Long Term Transmission Rights

IFA FR>GB

  1. Triggering event :

☒Curtailment to ensure operation remains within Operational Security Limits

☐Curtailment due to Force Majeure

☐Curtailment due to emergency situation

  1. Affected volume in MW / hour for each concerned period :

01/12/2021 – 31/12/2021

00:00 - 01:00        1399

01:00 - 02:00        1399

02:00 - 03:00        1399

03:00 - 04:00        1399

04:00 - 05:00        1399

05:00 - 06:00        1399

06:00 - 07:00        1399

07:00 - 08:00        1399

08:00 - 09:00        1399

09:00 - 10:00        1399

10:00 - 11:00        1399

11:00 - 12:00        1399

12:00 - 13:00        1399

13:00 - 14:00        1399

14:00 - 15:00        1399

15:00 - 16:00        1399

16:00 - 17:00        1399

17:00 - 18:00        1399

18:00 - 19:00        1399

19:00 - 20:00        1399

20:00 - 21:00        1399

21:00 - 22:00        1399

22:00 - 23:00        1399

23:00 - 00:00        1399

  1. Amount of LTTR remaining after curtailment :

01/12/2021 – 31/12/2021

00:00 - 01:00       1000

01:00 - 02:00       1000

02:00 - 03:00       1000

03:00 - 04:00       1000

04:00 - 05:00       1000

05:00 - 06:00       1000

06:00 - 07:00       1000

07:00 - 08:00       1000

08:00 - 09:00       1000

09:00 - 10:00       1000

10:00 - 11:00       1000

11:00 - 12:00       1000

12:00 - 13:00       1000

13:00 - 14:00       1000

14:00 - 15:00       1000

15:00 - 16:00       1000

16:00 - 17:00       1000

17:00 - 18:00       1000

18:00 - 19:00       1000

19:00 - 20:00       1000

20:00 - 21:00       1000

21:00 - 22:00       1000

22:00 - 23:00       1000

23:00 - 00:00       1000

  1. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:

Thermal Limits

  1. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?

Bipole 1 undergoing repair

GB > FR

  1. TSO(s) *:

National Grid Interconnectors Limited (NGIC) and RTE EDF Transport S.A. (RTE)

  1. Identification of affected Long Term Transmission Rights

IFA GB>FR

  1. Triggering event :

☒Curtailment to ensure operation remains within Operational Security Limits

☐Curtailment due to Force Majeure

☐Curtailment due to emergency situation

  1. Affected volume in MW / hour for each concerned period:

01/12/2021 – 31/12/2021

00:00 - 01:00        1399

01:00 - 02:00        1399

02:00 - 03:00        1399

03:00 - 04:00        1399

04:00 - 05:00        1399

05:00 - 06:00        1399

06:00 - 07:00        1399

07:00 - 08:00        1399

08:00 - 09:00        1399

09:00 - 10:00        1399

10:00 - 11:00        1399

11:00 - 12:00        1399

12:00 - 13:00        1399

13:00 - 14:00        1399

14:00 - 15:00        1399

15:00 - 16:00        1399

16:00 - 17:00        1399

17:00 - 18:00        1399

18:00 - 19:00        1399

19:00 - 20:00        1399

20:00 - 21:00        1399

21:00 - 22:00        1399

22:00 - 23:00        1399

23:00 - 00:00        1399

  1. Amount of LTTR remaining after curtailment:

01/12/2021 – 31/12/2021

00:00 - 01:00       1000

01:00 - 02:00       1000

02:00 - 03:00       1000

03:00 - 04:00       1000

04:00 - 05:00       1000

05:00 - 06:00       1000

06:00 - 07:00       1000

07:00 - 08:00       1000

08:00 - 09:00       1000

09:00 - 10:00       1000

10:00 - 11:00       1000

11:00 - 12:00       1000

12:00 - 13:00       1000

13:00 - 14:00       1000

14:00 - 15:00       1000

15:00 - 16:00       1000

16:00 - 17:00       1000

17:00 - 18:00       1000

18:00 - 19:00       1000

19:00 - 20:00       1000

20:00 - 21:00       1000

21:00 - 22:00       1000

22:00 - 23:00       1000

23:00 - 00:00       1000

  1. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:

Thermal Limits

  1. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?

Bipole 1 undergoing repair