Capacity Curtailment on the AT-IT border for 08/03/2022
Dear Colleagues,
Kindly find below the curtailment on the AT-IT border for market period 08/03/2022.
1. TSO(s)*:
APG
2. Identification of affected Long Term Transmission Rights
AT-IT
3. Triggering event :
ý Curtailment to ensure operation remains within Operational Security Limits |
o Curtailment due to Force Majeure |
o Curtailment due to emergency situation |
4. Affected volume in MW / hour for each concerned period : |
• 8/3/2022 |
• 08:00 - 09:00 90MW |
• 09:00 - 10:00 90MW |
• 10:00 - 11:00 90MW |
• 11:00 - 12:00 90MW |
• 12:00 - 13:00 90MW |
• 13:00 - 14:00 90MW |
• 14:00 - 15:00 90MW |
5. Amount of LTTR remaining after curtailment:
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:
Expected violation of operational security limits of physical transmission assets.
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?
During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation.
Regards,
JAO OPERATIONS