Capacity Curtailment on the AT-IT border for delivery 05-11-2023

Published:

1. TSO(s):

TERNA

2. Identification of affected Long Term Transmission Rights:

AT-IT

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

05-11-2023 00:00 - 01:00 152 MW

05-11-2023 01:00 - 02:00 152 MW

05-11-2023 02:00 - 03:00 152 MW

05-11-2023 03:00 - 04:00 152 MW

05-11-2023 04:00 - 05:00 152 MW

05-11-2023 05:00 - 06:00 152 MW

05-11-2023 06:00 - 07:00 152 MW

05-11-2023 07:00 - 08:00 152 MW

05-11-2023 08:00 - 09:00 152 MW

05-11-2023 09:00 - 10:00 152 MW

05-11-2023 10:00 - 11:00 152 MW

05-11-2023 11:00 - 12:00 152 MW

05-11-2023 12:00 - 13:00 152 MW

05-11-2023 13:00 - 14:00 152 MW

05-11-2023 14:00 - 15:00 152 MW

05-11-2023 15:00 - 16:00 152 MW

05-11-2023 16:00 - 17:00 152 MW

05-11-2023 21:00 - 22:00 152 MW

05-11-2023 22:00 - 23:00 152 MW

05-11-2023 23:00 - 24:00 152 MW

5. Amount of LTTR remaining after curtailment:

05-11-2023 00:00 - 01:00 72 MW

05-11-2023 01:00 - 02:00 43 MW

05-11-2023 02:00 - 03:00 43 MW

05-11-2023 03:00 - 04:00 43 MW

05-11-2023 04:00 - 05:00 43 MW

05-11-2023 05:00 - 06:00 50 MW

05-11-2023 06:00 - 07:00 50 MW

05-11-2023 07:00 - 08:00 46 MW

05-11-2023 08:00 - 09:00 53 MW

05-11-2023 09:00 - 10:00 55 MW

05-11-2023 10:00 - 11:00 43 MW

05-11-2023 11:00 - 12:00 46 MW

05-11-2023 12:00 - 13:00 40 MW

05-11-2023 13:00 - 14:00 35 MW

05-11-2023 14:00 - 15:00 52 MW

05-11-2023 15:00 - 16:00 78 MW

05-11-2023 16:00 - 17:00 104 MW

05-11-2023 21:00 - 22:00 128 MW

05-11-2023 22:00 - 23:00 104 MW

05-11-2023 23:00 - 24:00 78 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment:

Expected violation of operational security limits of physical transmission assets

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)?

During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation