Capacity Curtailment on the AT-IT border for delivery date 01-08-2024

Published:

1. TSO(s)*: TERNA

2. Identification of affected Long Term Transmission Rights:

AT-IT

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

01-08-2024 03:00 - 04:00 380 MW

01-08-2024 04:00 - 05:00 380 MW

01-08-2024 05:00 - 06:00 380 MW

01-08-2024 06:00 - 07:00 380 MW

01-08-2024 23:00 - 24:00 380 MW

5. Amount of LTTR remaining after curtailment:

01-08-2024 03:00 - 04:00 339 MW

01-08-2024 04:00 - 05:00 339 MW

01-08-2024 05:00 - 06:00 339 MW

01-08-2024 06:00 - 07:00 339 MW

01-08-2024 23:00 - 24:00 341 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:

Expected violation of operational security limits of physical transmission assets

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?

During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation

*According to section 57.3 of the EU HAR, this field can be filled in within 24 hours after the initial publication