Capacity Curtailment on the AT-IT border for delivery date 19-06-2024

Published:

1. TSO(s)*:

APG

2. Identification of affected Long Term Transmission Rights:

AT-IT

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

19-06-2024 08:00 - 09:00 237 MW

19-06-2024 09:00 - 10:00 237 MW

19-06-2024 10:00 - 11:00 237 MW

19-06-2024 11:00 - 12:00 237 MW

19-06-2024 12:00 - 13:00 237 MW

19-06-2024 13:00 - 14:00 237 MW

19-06-2024 14:00 - 15:00 237 MW

19-06-2024 15:00 - 16:00 237 MW

5. Amount of LTTR remaining after curtailment:

19-06-2024 08:00 - 09:00 140 MW

19-06-2024 09:00 - 10:00 140 MW

19-06-2024 10:00 - 11:00 140 MW

19-06-2024 11:00 - 12:00 140 MW

19-06-2024 12:00 - 13:00 141 MW

19-06-2024 13:00 - 14:00 141 MW

19-06-2024 14:00 - 15:00 141 MW

19-06-2024 15:00 - 16:00 140 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:

Expected violation of operational security limits of physical transmission assets.

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?

During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation.

*According to section 57.3 of the EU HAR, this field can be filled in within 24 hours after the initial publication