Capacity Curtailment on the AT-IT border for delivery day 20/06/2020

Published:

1. TSO(s) *:

2. Identification of affected Long Term Transmission Rights

Austria to Italy

3. Triggering event :

☒Curtailment to ensure operation remains within Operational Security Limits
☐Curtailment due to Force Majeure
☐Curtailment due to emergency situation

4. Affected volume in MW / hour for each concerned period :

Austria to Italy

20/06/2020

§ 10:00 – 11:00 90 MW

§ 11:00 – 12:00 90 MW

§ 12:00 – 13:00 90 MW

§ 13:00 – 14:00 90 MW

§ 14:00 – 15:00 90 MW

§ 15:00 – 16:00 90 MW

§ 16:00 – 17:00 90 MW

5. Amount of LTTR remaining after curtailment:

Austria to Italy

20/06/2020

§ 10:00 – 11:00 0 MW

§ 11:00 – 12:00 0 MW

§ 12:00 – 13:00 0 MW

§ 13:00 – 14:00 0 MW

§ 14:00 – 15:00 0 MW

§ 15:00 – 16:00 0 MW

§ 16:00 – 17:00 0 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?