Capacity Curtailment on the AT-IT border for delivery day 01/11/2022

Published:

1.TSO(s) *:

Terna

2. Identification of affected Long Term Transmission Rights

Austria to Italy

3. Triggering event:

 

☒Curtailment to ensure operation remains within Operational Security Limits
☐Curtailment due to Force Majeure
☐Curtailment due to emergency situation
 

4. Affected volume in MW / hour for each concerned period:

Austria to Italy

01/11/2022  

 

08:00 – 09:00  90 MW

09:00 – 10:00  90 MW

10:00 – 11:00  90 MW

11:00 – 12:00  90 MW

12:00 – 13:00  90 MW

13:00 – 14:00  90 MW

14:00 – 15:00  90 MW

 

5. Amount of LTTR remaining after curtailment:

Austria to Italy

01/11/2022  

 

08:00 – 09:00  79 MW

09:00 – 10:00  79 MW

10:00 – 11:00  79 MW

11:00 – 12:00  79 MW

12:00 – 13:00  79 MW

13:00 – 14:00  79 MW

14:00 – 15:00  79 MW

 

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:

Voltage stability issue on the Italian Electrical system

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?

During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation.