Capacity Curtailment on the IT-AT border for delivery day 13th and 14th of September

Published:

13th of September

1.              TSO(s) *:  TERNA; APG

 

2       Identification of affected Long Term Transmission Rights

               Italy to Austria

 

       3.       Triggering event:

 

☒Curtailment to ensure operation remains within Operational Security Limits
☐Curtailment due to Force Majeure
☐Curtailment due to emergency situation
 

4.       Affected volume in MW / hour for each concerned period:

         Italy to Austria

 

13/09/2020

 

00:00 – 01:00  50 MW

01:00 – 02:00  50 MW

02:00 – 03:00  50 MW

03:00 – 04:00  50 MW

04:00 – 05:00  50 MW

05:00 – 06:00  50 MW

06:00 – 07:00  50 MW

07:00 – 08:00  50 MW

08:00 – 09:00  50 MW

09:00 – 10:00  50 MW

10:00 – 11:00  50 MW

11:00 – 12:00  50 MW

12:00 – 13:00  50 MW

13:00 – 14:00  50 MW

14:00 – 15:00  50 MW

15:00 – 16:00  50 MW

16:00 – 17:00  50 MW

17:00 – 18:00  50 MW

18:00 – 19:00  50 MW

19:00 – 20:00  50 MW

20:00 – 21:00  50 MW

21:00 – 22:00  50 MW

22:00 – 23:00  50 MW

23:00 – 24:00  50 MW 

 

5. Amount of LTTR remaining after curtailment:

Italy to Austria

13/09/2020

 

00:00 – 01:00  9 MW

01:00 – 02:00  9 MW

02:00 – 03:00  9 MW

03:00 – 04:00  9 MW

04:00 – 05:00  9 MW

05:00 – 06:00  9 MW

06:00 – 07:00  9 MW

07:00 – 08:00  9 MW

08:00 – 09:00  9 MW

09:00 – 10:00  9 MW

10:00 – 11:00  9 MW

11:00 – 12:00  9 MW

12:00 – 13:00  9 MW

13:00 – 14:00  9 MW

14:00 – 15:00  9 MW

15:00 – 16:00  9 MW

16:00 – 17:00  9 MW

17:00 – 18:00  9 MW

18:00 – 19:00  9 MW

19:00 – 20:00  9 MW

20:00 – 21:00  9 MW

21:00 – 22:00  9 MW

22:00 – 23:00  9 MW

23:00 – 24:00  9 MW 

 

         

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:  

     Outage of Soverzene-Lienz

 

7.Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?

     During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation

 

 

 

14th of September

 

1.       TSO(s) *:  TERNA; APG

 

2.       Identification of affected Long Term Transmission Rights

         Italy to Austria

 

3.       Triggering event:

 

☒Curtailment to ensure operation remains within Operational Security Limits
☐Curtailment due to Force Majeure
☐Curtailment due to emergency situation
 

4.       Affected volume in MW / hour for each concerned period:

         Italy to Austria

 

14/09/2020

 

00:00 – 01:00  60 MW

01:00 – 02:00  60 MW

02:00 – 03:00  60 MW

03:00 – 04:00  60 MW

04:00 – 05:00  60 MW

05:00 – 06:00  60 MW

06:00 – 07:00  60 MW

07:00 – 08:00  60 MW

08:00 – 09:00  60 MW

09:00 – 10:00  60 MW

10:00 – 11:00  60 MW

11:00 – 12:00  60 MW

12:00 – 13:00  60 MW

13:00 – 14:00  60 MW

14:00 – 15:00  60 MW

15:00 – 16:00  60 MW

16:00 – 17:00  60 MW

 

5. Amount of LTTR remaining after curtailment:

Italy to Austria

14/09/2020

 

00:00 – 01:00  6 MW

01:00 – 02:00  6 MW

02:00 – 03:00  6 MW

03:00 – 04:00  6 MW

04:00 – 05:00  6 MW

05:00 – 06:00  6 MW

06:00 – 07:00  6 MW

07:00 – 08:00  6 MW

08:00 – 09:00  6 MW

09:00 – 10:00  6 MW

10:00 – 11:00  6 MW

11:00 – 12:00  6 MW

12:00 – 13:00  6 MW

13:00 – 14:00  6 MW

14:00 – 15:00  6 MW

15:00 – 16:00  6 MW

16:00 – 17:00  6 MW

 

         

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:  

   Outage of Soverzene-Lienz

 

 

7.Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?

     During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation