Capacity Curtailment on the AT-IT border for delivery day 21/03/2021
1. TSO(s) *:
Swissgrid,TERNA
2. Identification of affected Long Term Transmission Rights
Austria to Italy
3. Triggering event
☒Curtailment to ensure operation remains within Operational Security Limits
☐Curtailment due to Force Majeure
☐Curtailment due to emergency situation
4.Affected volume in MW / hour for each concerned period:
Austria to Italy
21/03/2021
10:00 - 11:00 60 MW
11:00 – 12:00 60 MW
15:00 – 16:00 60 MW
16:00 – 17:00 60 MW
5.Amount of LTTR remaining after curtailment:
Austria to Italy
21/03/2021
10:00 - 11:00 47 MW
11:00 – 12:00 51 MW
15:00 – 16:00 51 MW
16:00 – 17:00 36 MW
6.Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:
For period
10:00 - 11:00 47 MW
11:00 – 12:00 51 MW
Reduction due to the following overloaded element(s): Lienz-Soverzene (137,8%)
For period
15:00 – 16:00 51 MW
16:00 – 17:00 36 MW
Reduction due to an incorrect calculation of the Coreso d-2; Terna entered the previously programmed NTC values.
7.Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?
During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation