Capacity Curtailment on the AT-IT border for delivery day 09/12/2021

Published:

1. TSO(s)*:
APG

2. Identification of affected Long Term Transmission Rights
AT-IT

3. Triggering event :

ý Curtailment to ensure operation remains within Operational Security Limits

o Curtailment due to Force Majeure

o Curtailment due to emergency situation

4. Affected volume in MW / hour for each concerned period :

         • 02:00 - 03:00 172MW

         • 03:00 - 04:00 170MW

         • 04:00 - 05:00 180MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:


7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?