Capacity Curtailment on the IT-AT border for delivery day 14/09/2022

Published:

1. TSO(s)*:
APG

2. Identification of affected Long Term Transmission Rights
IT-AT

3. Triggering event :

ý Curtailment to ensure operation remains within Operational Security Limits

o Curtailment due to Force Majeure

o Curtailment due to emergency situation

4. Affected volume in MW / hour for each concerned period :

    • 14/9/2022

         • 08:00 - 09:00 31MW

         • 09:00 - 10:00 31MW

         • 10:00 - 11:00 31MW

         • 11:00 - 12:00 31MW


5. Amount of LTTR remaining after curtailment:

    • 14/9/2022

         • 08:00 - 09:00 7MW

         • 09:00 - 10:00 7MW

         • 10:00 - 11:00 7MW

         • 11:00 - 12:00 7MW



6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:
Expected violation of operational security limits of physical transmission assets.

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?
During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation.