Capacity Curtailment on the IT-AT border for delivery days from 03/09/2020 to 12/09/2020

Published:

1.       TSO(s) *:  TERNA

 

2.       Identification of affected Long Term Transmission Rights

         Italy to Austria

 

3.       Triggering event:

 

☒Curtailment to ensure operation remains within Operational Security Limits
☐Curtailment due to Force Majeure
☐Curtailment due to emergency situation
 

4.       Affected volume in MW / hour for each concerned period:

         Italy to Austria

 

From 03/09/2020 to 12/09/2020

 

00:00 – 01:00  50 MW

01:00 – 02:00  50 MW

02:00 – 03:00  50 MW

03:00 – 04:00  50 MW

04:00 – 05:00  50 MW

05:00 – 06:00  50 MW

06:00 – 07:00  50 MW

07:00 – 08:00  50 MW

08:00 – 09:00  50 MW

09:00 – 10:00  50 MW

10:00 – 11:00  50 MW

11:00 – 12:00  50 MW

12:00 – 13:00  50 MW

13:00 – 14:00  50 MW

14:00 – 15:00  50 MW

15:00 – 16:00  50 MW

16:00 – 17:00  50 MW

17:00 – 18:00  50 MW

18:00 – 19:00  50 MW

19:00 – 20:00  50 MW

20:00 – 21:00  50 MW

21:00 – 22:00  50 MW

22:00 – 23:00  50 MW

23:00 – 24:00  50 MW 

 

5. Amount of LTTR remaining after curtailment:

Italy to Austria

From 03/09/2020 to 12/09/2020

 

00:00 – 01:00  9 MW

01:00 – 02:00  9 MW

02:00 – 03:00  9 MW

03:00 – 04:00  9 MW

04:00 – 05:00  9 MW

05:00 – 06:00  9 MW

06:00 – 07:00  9 MW

07:00 – 08:00  9 MW

08:00 – 09:00  9 MW

09:00 – 10:00  9 MW

10:00 – 11:00  9 MW

11:00 – 12:00  9 MW

12:00 – 13:00  9 MW

13:00 – 14:00  9 MW

14:00 – 15:00  9 MW

15:00 – 16:00  9 MW

16:00 – 17:00  9 MW

17:00 – 18:00  9 MW

18:00 – 19:00  9 MW

19:00 – 20:00  9 MW

20:00 – 21:00  9 MW

21:00 – 22:00  9 MW

22:00 – 23:00  9 MW

23:00 – 24:00  9 MW 

 

         

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:  

         Voltage stability issue on the Italian Electrical system 

 

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?

            During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation