Capacity Curtailment on the AT-IT border for delivery period 04-03-2026

Published:

1. TSO(s)*:

APG & TERNA

2. Identification of affected Long Term Transmission Rights:

AT-IT

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

04-03-2026 07:00 - 08:00 149 MW

04-03-2026 08:00 - 09:00 149 MW

04-03-2026 09:00 - 10:00 149 MW

04-03-2026 10:00 - 11:00 149 MW

04-03-2026 11:00 - 12:00 149 MW

04-03-2026 12:00 - 13:00 149 MW

04-03-2026 13:00 - 14:00 149 MW

04-03-2026 14:00 - 15:00 149 MW

04-03-2026 15:00 - 16:00 149 MW

04-03-2026 16:00 - 17:00 149 MW

5. Amount of LTTR remaining after curtailment:

04-03-2026 07:00 - 08:00 121 MW

04-03-2026 08:00 - 09:00 131 MW

04-03-2026 09:00 - 10:00 131 MW

04-03-2026 10:00 - 11:00 131 MW

04-03-2026 11:00 - 12:00 131 MW

04-03-2026 12:00 - 13:00 131 MW

04-03-2026 13:00 - 14:00 131 MW

04-03-2026 14:00 - 15:00 131 MW

04-03-2026 15:00 - 16:00 131 MW

04-03-2026 16:00 - 17:00 131 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:

Expected violation of operational security limits of physical transmission assets.

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?

During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation.