Capacity Curtailment on the IT-AT border for delivery period 08-07-2025
1. TSO(s)*:
APG
2. Identification of affected Long Term Transmission Rights:
IT-AT
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Affected volume in MW / hour for each concerned period:
08-07-2025 13:00 - 14:00 79 MW
08-07-2025 14:00 - 15:00 79 MW
08-07-2025 15:00 - 16:00 79 MW
08-07-2025 16:00 - 17:00 79 MW
5. Amount of LTTR remaining after curtailment:
08-07-2025 13:00 - 14:00 59 MW
08-07-2025 14:00 - 15:00 59 MW
08-07-2025 15:00 - 16:00 59 MW
08-07-2025 16:00 - 17:00 59 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:
Expected violation of operational security limits of physical transmission assets.
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?
During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation.