Capacity Curtailment on the AT-IT border for delivery period 12-12-2024
1. TSO(s)*:
TERNA
2. Identification of affected Long Term Transmission Rights:
AT-IT
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Affected volume in MW / hour for each concerned period:
12-12-2024 07:00 - 08:00 237 MW
12-12-2024 08:00 - 09:00 237 MW
12-12-2024 15:00 - 16:00 237 MW
12-12-2024 16:00 - 17:00 237 MW
12-12-2024 17:00 - 18:00 237 MW
12-12-2024 18:00 - 19:00 237 MW
12-12-2024 19:00 - 20:00 237 MW
12-12-2024 20:00 - 21:00 237 MW
5. Amount of LTTR remaining after curtailment:
12-12-2024 07:00 - 08:00 189 MW
12-12-2024 08:00 - 09:00 177 MW
12-12-2024 15:00 - 16:00 140 MW
12-12-2024 16:00 - 17:00 140 MW
12-12-2024 17:00 - 18:00 140 MW
12-12-2024 18:00 - 19:00 140 MW
12-12-2024 19:00 - 20:00 140 MW
12-12-2024 20:00 - 21:00 140 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:
Expected violation of operational security limits of physical transmission assets.
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?
During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation.