Capacity Curtailment on the IT-AT border for delivery period 16-11-2025

Published:

1. TSO(s)*:

APG

2. Identification of affected Long Term Transmission Rights:

IT-AT

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

16-11-2025 13:00 - 14:00 106 MW

16-11-2025 14:00 - 15:00 106 MW

16-11-2025 15:00 - 16:00 106 MW

16-11-2025 16:00 - 17:00 106 MW

16-11-2025 17:00 - 18:00 106 MW

16-11-2025 18:00 - 19:00 106 MW

16-11-2025 19:00 - 20:00 106 MW

16-11-2025 20:00 - 21:00 106 MW

16-11-2025 21:00 - 22:00 106 MW

16-11-2025 22:00 - 23:00 106 MW

16-11-2025 23:00 - 24:00 106 MW

5. Amount of LTTR remaining after curtailment:

16-11-2025 13:00 - 14:00 58 MW

16-11-2025 14:00 - 15:00 58 MW

16-11-2025 15:00 - 16:00 58 MW

16-11-2025 16:00 - 17:00 58 MW

16-11-2025 17:00 - 18:00 58 MW

16-11-2025 18:00 - 19:00 58 MW

16-11-2025 19:00 - 20:00 58 MW

16-11-2025 20:00 - 21:00 58 MW

16-11-2025 21:00 - 22:00 58 MW

16-11-2025 22:00 - 23:00 58 MW

16-11-2025 23:00 - 24:00 58 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:

Expected violation of operational security limits of physical transmission assets.

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?

During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation