Capacity Curtailment on the AT-IT border for delivery period 20-10-2024

Published:

1. TSO(s)*:

TERNA

2. Identification of affected Long Term Transmission Rights:

AT-IT

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

20-10-2024 01:00 - 02:00 201 MW

20-10-2024 02:00 - 03:00 201 MW

20-10-2024 03:00 - 04:00 201 MW

20-10-2024 04:00 - 05:00 201 MW

20-10-2024 05:00 - 06:00 201 MW

20-10-2024 06:00 - 07:00 201 MW

20-10-2024 07:00 - 08:00 201 MW

20-10-2024 08:00 - 09:00 201 MW

20-10-2024 09:00 - 10:00 201 MW

20-10-2024 10:00 - 11:00 201 MW

20-10-2024 11:00 - 12:00 201 MW

20-10-2024 12:00 - 13:00 201 MW

20-10-2024 13:00 - 14:00 201 MW

20-10-2024 14:00 - 15:00 201 MW

20-10-2024 15:00 - 16:00 201 MW

20-10-2024 16:00 - 17:00 201 MW

20-10-2024 17:00 - 18:00 201 MW

20-10-2024 23:00 - 24:00 201 MW

5. Amount of LTTR remaining after curtailment:

20-10-2024 01:00 - 02:00 153 MW

20-10-2024 02:00 - 03:00 53 MW

20-10-2024 03:00 - 04:00 0 MW

20-10-2024 04:00 - 05:00 0 MW

20-10-2024 05:00 - 06:00 1 MW

20-10-2024 06:00 - 07:00 1 MW

20-10-2024 07:00 - 08:00 25 MW

20-10-2024 08:00 - 09:00 76 MW

20-10-2024 09:00 - 10:00 76 MW

20-10-2024 10:00 - 11:00 37 MW

20-10-2024 11:00 - 12:00 63 MW

20-10-2024 12:00 - 13:00 37 MW

20-10-2024 13:00 - 14:00 0 MW

20-10-2024 14:00 - 15:00 0 MW

20-10-2024 15:00 - 16:00 0 MW

20-10-2024 16:00 - 17:00 53 MW

20-10-2024 17:00 - 18:00 141 MW

20-10-2024 23:00 - 24:00 178 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:

Expected violation of operational security limits of physical transmission assets

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?

During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation