Capacity Curtailment on the AT-IT border for delivery period 22-09-2024
1. TSO(s)*:
TERNA
2. Identification of affected Long Term Transmission Rights:
AT-IT
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Affected volume in MW / hour for each concerned period:
22-09-2024 10:00 - 11:00 197 MW
22-09-2024 11:00 - 12:00 197 MW
22-09-2024 12:00 - 13:00 197 MW
22-09-2024 13:00 - 14:00 197 MW
22-09-2024 14:00 - 15:00 197 MW
22-09-2024 15:00 - 16:00 197 MW
22-09-2024 16:00 - 17:00 197 MW
5. Amount of LTTR remaining after curtailment:
22-09-2024 10:00 - 11:00 122 MW
22-09-2024 11:00 - 12:00 59 MW
22-09-2024 12:00 - 13:00 11 MW
22-09-2024 13:00 - 14:00 5 MW
22-09-2024 14:00 - 15:00 26 MW
22-09-2024 15:00 - 16:00 92 MW
22-09-2024 16:00 - 17:00 153 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:
Expected violation of operational security limits of physical transmission assets
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?
During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation