Capacity Curtailment on the AT-IT border for market period 26/09/2022

Published:
  1. TSO(s) *:  TERNA

 

  1. Identification of affected Long Term Transmission Rights

  

Austria to Italy

 

  1. Triggering event :

 

☒Curtailment to ensure operation remains within Operational Security Limits

☐Curtailment due to Force Majeure

☐Curtailment due to emergency situation

 

  1. Affected volume in MW / hour for each concerned period :

Austria to Italy

 

26/09/2022  

      • 00:00 – 01:00  89 MW
      • 01:00 – 02:00  89 MW
      • 02:00 – 03:00  89 MW
      • 03:00 – 04:00  89 MW
      • 04:00 – 05:00  89MW
      • 05:00 – 06:00  89 MW
      • 06:00 – 07:00  89 MW
      • 07:00 – 08:00  89 MW
      • 08:00 – 09:00  89 MW
      • 09:00 – 10:00  89 MW
      • 10:00 – 11:00  89 MW
      • 11:00 – 12:00  89 MW
      • 12:00 – 13:00  89 MW
      • 13:00 – 14:00  89 MW
      • 14:00 – 15:00  89 MW
      • 15:00 – 16:00  89 MW
      • 16:00 – 17:00  89 MW
      • 17:00 – 18:00  89 MW
      • 18:00 – 19:00  89 MW
      • 19:00 – 20:00  89 MW
      • 89:00 – 21:00  89 MW
      • 21:00 – 22:00  89 MW
      • 22:00 – 23:00  89 MW
      • 23:00 – 24:00  89 MW

 

  1. Amount of LTTR remaining after curtailment :

       Austria to Italy

 

26/09/2022  

      • 00:00 – 01:00  69 MW
      • 01:00 – 02:00  69 MW
      • 02:00 – 03:00  69 MW
      • 03:00 – 04:00  69 MW
      • 04:00 – 05:00  70MW
      • 05:00 – 06:00  70 MW
      • 06:00 – 07:00  70 MW
      • 07:00 – 08:00  70 MW
      • 08:00 – 09:00  70 MW
      • 09:00 – 10:00  71 MW
      • 10:00 – 11:00  71 MW
      • 11:00 – 12:00  71 MW
      • 12:00 – 13:00  71 MW
      • 13:00 – 14:00  71 MW
      • 14:00 – 15:00  71 MW
      • 15:00 – 16:00  70 MW
      • 16:00 – 17:00  70 MW
      • 17:00 – 18:00  70 MW
      • 18:00 – 19:00  71 MW
      • 19:00 – 20:00  71 MW
      • 20:00 – 21:00  71 MW
      • 21:00 – 22:00  70 MW
      • 22:00 – 23:00  70 MW
      • 23:00 – 24:00  62 MW

 

  

 

  1. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:

 

                Expected violation of operational security limits of physical transmission assets.

 

 

  1. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?

 

                During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation.