Capacity Curtailment on the IT-FR border for delivery date 10-06-2024

Published:

1. TSO(s)*:

Terna-RTE

2. Identification of affected Long Term Transmission Rights:

IT-FR

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

10-06-2024 08:00 - 09:00 1868 MW

10-06-2024 09:00 - 10:00 1868 MW

10-06-2024 10:00 - 11:00 1868 MW

10-06-2024 11:00 - 12:00 1868 MW

10-06-2024 12:00 - 13:00 1868 MW

10-06-2024 13:00 - 14:00 1868 MW

10-06-2024 14:00 - 15:00 1868 MW

10-06-2024 15:00 - 16:00 1868 MW

10-06-2024 16:00 - 17:00 1868 MW

10-06-2024 17:00 - 18:00 1868 MW

10-06-2024 18:00 - 19:00 1868 MW

10-06-2024 19:00 - 20:00 1868 MW

10-06-2024 20:00 - 21:00 1868 MW

10-06-2024 21:00 - 22:00 1868 MW

10-06-2024 22:00 - 23:00 1868 MW

10-06-2024 23:00 - 24:00 1868 MW

5. Amount of LTTR remaining after curtailment:

10-06-2024 08:00 - 09:00 1357 MW

10-06-2024 09:00 - 10:00 1357 MW

10-06-2024 10:00 - 11:00 1357 MW

10-06-2024 11:00 - 12:00 1357 MW

10-06-2024 12:00 - 13:00 1357 MW

10-06-2024 13:00 - 14:00 1357 MW

10-06-2024 14:00 - 15:00 1357 MW

10-06-2024 15:00 - 16:00 1357 MW

10-06-2024 16:00 - 17:00 1357 MW

10-06-2024 17:00 - 18:00 1357 MW

10-06-2024 18:00 - 19:00 1357 MW

10-06-2024 19:00 - 20:00 1357 MW

10-06-2024 20:00 - 21:00 1357 MW

10-06-2024 21:00 - 22:00 1357 MW

10-06-2024 22:00 - 23:00 1357 MW

10-06-2024 23:00 - 24:00 1534 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:

Expected violation of operational security limits of physical transmission assets

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?

During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation