Capacity Curtailment on the IT-FR border for delivery period 21-01-2026
1. TSO(s)*:
TERNA
2. Identification of affected Long Term Transmission Rights:
IT-FR
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Affected volume in MW / hour for each concerned period:
21-01-2026 05:00 - 06:00 1495 MW
21-01-2026 06:00 - 07:00 1495 MW
21-01-2026 07:00 - 08:00 1495 MW
21-01-2026 08:00 - 09:00 1495 MW
21-01-2026 09:00 - 10:00 1495 MW
21-01-2026 10:00 - 11:00 1495 MW
21-01-2026 11:00 - 12:00 1495 MW
5. Amount of LTTR remaining after curtailment:
21-01-2026 05:00 - 06:00 1422 MW
21-01-2026 06:00 - 07:00 804 MW
21-01-2026 07:00 - 08:00 176 MW
21-01-2026 08:00 - 09:00 176 MW
21-01-2026 09:00 - 10:00 176 MW
21-01-2026 10:00 - 11:00 788 MW
21-01-2026 11:00 - 12:00 1400 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:
Expected violation of operational security limits of physical transmission assets
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?
During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC
*According to section 57.3 of the EU HAR, this field can be filled in within 24 hours after the initial publication