Capacity Curtailment: AT-IT, FR-IT, CH-IT, and SI-IT for delivery date 07/01/2019

Published:

Dear Market Participants,

The long-term allocated capacities for delivery date 07/01/2019 on the corridors from Austria to Italy, from France to Italy, from Switzerland to Italy and from Slovenia to Italy have been curtailed to ensure operation remains within Operational Security Limits.

AT>IT:

From position 1 to position 3 it was reduced to 137 MWs

From position 4 to position 5 it was reduced to 120 MWs

On position 6 it was reduced to 140 MWs

On position 7 it was reduced to 141 MWs

On position 8 it was reduced to 188 MWs

On position 9 it was reduced to 198 MWs

FR>IT:

From position 4 to position 5 it was reduced to 930 MWs

On position 6 it was reduced to 903 MWs

CH>IT:

From position 1 to position 3 it was reduced to 59%

From position 4 to position 5 it was reduced to 49%

On position 6 it was reduced to 43%

On position 7 it was reduced to 41%

On position 8 it was reduced to 84%

On position 9 it was reduced to 70%

From position 10 to position 12 it was reduced to 96%

From position 13 to position 15 it was reduced to 94%

From position 16 to position 18 it was reduced to 88%

From position 19 to position 20 it was reduced to 96%

SI>IT:

From position 1 to position 3 it was reduced to 218 MWs

From position 4 to position 5 it was reduced to 182 MWs

On position 6 it was reduced to 192 MWs

On position 7 it was reduced to 185 MWs

On position 8 it was reduced to 343 MWs

Please consider the latest version of the programming authorizations.

Kind regards,

Operations Team

JAO S.A.

2 rue de Bitbourg

L-1273 Luxembourg-Hamm

T. +352 27 62 38 38