Capacity Curtailment on the IT-SI border for delivery period 23-09-2024
1. TSO(s)*:
TERNA
2. Identification of affected Long Term Transmission Rights:
IT-SI
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Affected volume in MW / hour for each concerned period:
23-09-2024 07:00 - 08:00 315 MW
23-09-2024 08:00 - 09:00 315 MW
5. Amount of LTTR remaining after curtailment:
23-09-2024 07:00 - 08:00 262 MW
23-09-2024 08:00 - 09:00 235 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:
Expected violation of operational security limits of physical transmission assets
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?
During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation