Capacity Curtailment on the IT-SI border for delivery period 21-11-2024
1. TSO(s)*:
TERNA
2. Identification of affected Long Term Transmission Rights:
IT-SI
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Affected volume in MW / hour for each concerned period:
21-11-2024 18:00 - 19:00 333 MW
21-11-2024 19:00 - 20:00 333 MW
21-11-2024 20:00 - 21:00 333 MW
5. Amount of LTTR remaining after curtailment:
21-11-2024 18:00 - 19:00 303 MW
21-11-2024 19:00 - 20:00 304 MW
21-11-2024 20:00 - 21:00 304 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:
Expected violation of operational security limits of physical transmission assets
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?
During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC