Capacity Curtailment on the IT<>AT border for delivery 11-12-2023

Published:
v\:* {behavior:url(#default#VML);} o\:* {behavior:url(#default#VML);} w\:* {behavior:url(#default#VML);} .shape {behavior:url(#default#VML);}

1. TSO(s)*:

TERNA-APG

2. Identification of affected Long Term Transmission Rights:

IT-AT

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

11-12-2023 13:00 - 14:00 46 MW

11-12-2023 14:00 - 15:00 46 MW

11-12-2023 15:00 - 16:00 46 MW

11-12-2023 16:00 - 17:00 46 MW

11-12-2023 17:00 - 18:00 46 MW

11-12-2023 18:00 - 19:00 46 MW

11-12-2023 19:00 - 20:00 46 MW

11-12-2023 20:00 - 21:00 46 MW

11-12-2023 21:00 - 22:00 46 MW

11-12-2023 22:00 - 23:00 46 MW

11-12-2023 23:00 - 24:00 46 MW

5. Amount of LTTR remaining after curtailment:

11-12-2023 13:00 - 14:00 0 MW

11-12-2023 14:00 - 15:00 0 MW

11-12-2023 15:00 - 16:00 0 MW

11-12-2023 16:00 - 17:00 0 MW

11-12-2023 17:00 - 18:00 0 MW

11-12-2023 18:00 - 19:00 0 MW

11-12-2023 19:00 - 20:00 0 MW

11-12-2023 20:00 - 21:00 0 MW

11-12-2023 21:00 - 22:00 0 MW

11-12-2023 22:00 - 23:00 0 MW

11-12-2023 23:00 - 24:00 0 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:

Expected violation of operational security limits of physical transmission assets

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?

During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation

*According to section 57.3 of the EU HAR, this field can be filled in within 24 hours after the initial publication

1. TSO(s)*:

TERNA-APG

2. Identification of affected Long Term Transmission Rights:

AT-IT

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

11-12-2023 02:00 - 03:00 152 MW 

11-12-2023 13:00 - 14:00 152 MW

11-12-2023 14:00 - 15:00 152 MW

11-12-2023 15:00 - 16:00 152 MW

11-12-2023 16:00 - 17:00 152 MW

11-12-2023 17:00 - 18:00 152 MW

11-12-2023 18:00 - 19:00 152 MW

11-12-2023 19:00 - 20:00 152 MW

11-12-2023 20:00 - 21:00 152 MW

11-12-2023 21:00 - 22:00 152 MW

11-12-2023 22:00 - 23:00 152 MW

11-12-2023 23:00 - 24:00 152 MW

5. Amount of LTTR remaining after curtailment:

11-12-2023 02:00 - 03:00 128 MW 

11-12-2023 13:00 - 14:00 0 MW

11-12-2023 14:00 - 15:00 0 MW

11-12-2023 15:00 - 16:00 0 MW

11-12-2023 16:00 - 17:00 0 MW

11-12-2023 17:00 - 18:00 0 MW

11-12-2023 18:00 - 19:00 0 MW

11-12-2023 19:00 - 20:00 0 MW

11-12-2023 20:00 - 21:00 0 MW

11-12-2023 21:00 - 22:00 0 MW

11-12-2023 22:00 - 23:00 0 MW

11-12-2023 23:00 - 24:00 0 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:

Expected violation of operational security limits of physical transmission assets

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?

During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation

*According to section 57.3 of the EU HAR, this field can be filled in within 24 hours after the initial publication