Capacity Curtailment on the ME-IT border for delivery period 08-04-2026

Published:

1. TSO(s)*:

TERNA

2. Identification of affected Long Term Transmission Rights:

ME-IT

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

08-04-2026 08:00 - 09:00 400 MW

08-04-2026 09:00 - 10:00 400 MW

08-04-2026 10:00 - 11:00 400 MW

08-04-2026 11:00 - 12:00 400 MW

5. Amount of LTTR remaining after curtailment:

08-04-2026 08:00 - 09:00 0 MW

08-04-2026 09:00 - 10:00 0 MW

08-04-2026 10:00 - 11:00 0 MW

08-04-2026 11:00 - 12:00 0 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?

*According to section 57.3 of the EU HAR, this field can be filled in within 24 hours after the initial publication