Capacity Curtailment on the NL-BE border for delivery 13-02-2023
1. TSO(s)*:
TenneT_NL
2. Identification of affected Long Term Transmission Rights:
NL-BE
3. Triggering event :
☒Curtailment to ensure operation remains within Operational Security Limits
☐Curtailment due to Force Majeure
☐Curtailment due to emergency situation
☒Adjusted because of expected violation of operational security
☒Adjusted because already considered remedial actions are assessed as not sufficient
4. Affected volume in MW / hour for each concerned period:
13-02-2023 08:00 - 09:00 619 MW
13-02-2023 16:00 - 17:00 619 MW
5. Amount of LTTR remaining after curtailment:
13-02-2023 08:00 - 09:00 152 MW
13-02-2023 16:00 - 17:00 152 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:Expected violation of operational security limits of physical transmission assets.
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?The remedial actions considered in the FB DA CC process were assessed as not sufficient or ineffective to avoid the expected violation of operational security limit(s).