Capacity Curtailment on the NL > BE border for delivery day 22/11/2022
1.TSO(s) *:
Tennet NL
2.Identification of affected Long Term Transmission Rights
NL > BE 22/11/2022
3.Triggering event :
☒Curtailment to ensure operation remains within Operational Security Limits |
☐Curtailment due to Force Majeure |
☐Curtailment due to emergency situation |
4.Affected volume in MW / hour for each concerned period :
NL > BE 22/11/2022:
00:00- 23:59 : 619MW
5.Amount of LTTR remaining after curtailment :
NL>BE 22/11/2022 :
00:00-09:00 : 619MW
09:00-10:00 : 468 MW
10:00-11:00 : 619MW
6.Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:
Excepted violation security
7.Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?
Remedial not sufficient
*According to section 57.3 of the EU HAR, this field can be filled in within 24 hours after the initial publication