Capacity Curtailment on NL-BE & FR-IT borders for delivery day 28/10/2019

Published:

Dear Market Participants,

The long-term allocated capacities for delivery date 28/10/2019 on corridor from the Netherlands to Belgium, and from France to Italy have been curtailed to ensure operation remains within Operational Security Limits.

NL>BE

On position 8 it was reduced to 503 MW

FR>IT

From position 1 to position 3 it was reduced to 1571 MW
From position 4 to position 7 it was reduced to 1598 MW
From position 8 to position 9 it was reduced to 1542 MW
From position 10 to position 11 it was reduced to 1561 MW
On position 12 it was reduced to 1732 MW
From position 13 to position 16 it was reduced to 1561 MW
From position 17 to position 23 it was reduced to 1542 MW
On position 24 it was reduced to 1512 MW

Please consider the latest version of the programming authorizations.