Capacity Curtailment on the NL-DE border for delivery day 25/11/2021

Published:

1.TSO(s): TenneT TSO B.V.

2.Identification of affected Long Term Transmission Rights

Netherlands -> Germany

3.Triggering event :

☒Curtailment to ensure operation remains within Operational Security Limits

☐Curtailment due to Force Majeure

☐Curtailment due to emergency situation

4.Affected volume in MW / hour for each concerned period :

25/11/2021:

Netherlands -> Germany:
• 06:00 - 07:00: 1081 MW
• 07:00 - 08:00: 1081 MW
• 08:00 - 09:00: 1081 MW
• 09:00 - 10:00: 1081 MW
• 10:00 - 11:00: 1081 MW
• 11:00 - 12:00: 1081 MW
• 12:00 - 13:00: 1081 MW
• 13:00 - 14:00: 1081 MW
• 14:00 - 15:00: 1081 MW
• 15:00 - 16:00: 1081 MW
• 17:00 - 18:00: 1081 MW
• 18:00 - 19:00: 1081 MW
• 19:00 - 20:00: 1081 MW
• 20:00 - 21:00: 1081 MW

5.Amount of LTTR remaining after curtailment :

25/11/2021:

Netherlands -> Germany:
                • 06:00 - 07:00: 631 MW
                • 07:00 - 08:00: 631 MW
                • 08:00 - 09:00: 631 MW
                • 09:00 - 10:00: 631 MW
                • 10:00 - 11:00: 631 MW
                • 11:00 - 12:00: 631 MW
                • 12:00 - 13:00: 631 MW
                • 13:00 - 14:00: 631 MW
                • 14:00 - 15:00: 631 MW
                • 15:00 - 16:00: 631 MW
                • 17:00 - 18:00: 631 MW
                • 18:00 - 19:00: 631 MW
                • 19:00 - 20:00: 631 MW
                • 20:00 - 21:00: 631 MW

6.Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:

Expected violation of operational security limits of physical transmission assets.

7.Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?

The remedial actions considered in the FB DA CC process were assessed as not sufficient or ineffective to avoid the expected violation of operational security limit(s).