Capacity Curtailment on the NL-DE border for delivery day 17/03/2022
Dear Market Participant,
1.TSO(s): TenneT TSO B.V.
2.Identification of affected Long Term Transmission Rights
Netherlands -> Germany
3.Triggering event :
☒Curtailment to ensure operation remains within Operational Security Limits |
☐Curtailment due to Force Majeure |
☐Curtailment due to emergency situation |
4.Affected volume in MW / hour for each concerned period :
17/03/2022:
Netherlands -> Germany:
• 19:00 - 20:00: 1081 MW
5.Amount of LTTR remaining after curtailment :
17/03/2022:
Netherlands -> Germany:
• 19:00 - 20:00: 978 MW
6.Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:
Expected violation of operational security limits of physical transmission assets.
7.Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?
The remedial actions considered in the FB DA CC process were assessed as not sufficient or ineffective to avoid the expected violation of operational security limit(s)