Capacity Curtailment on the NL-DE border for delivery day 16/06/2022

Published:

1.         TSO(s):

TenneT TSO B.V.

 

2.         Identification of affected Long Term Transmission Rights

Netherlands -> Germany

 

3.         Triggering event :

 

Curtailment to ensure operation remains within Operational Security Limits

Curtailment due to Force Majeure

Curtailment due to emergency situation

Adjusted because of expected violation of operational security

Adjusted because already considered remedial actions are assessed as not sufficient

 

 

4.         Affected volume in MW / hour for each concerned period :

16/06/2022:

Netherlands -> Germany:

15:00 – 16:00  1081 MW

 

5. Amount of LTTR remaining after curtailment :

16/06/2022:

Netherlands -> Germany:

15:00 – 16:00  469 MW

 

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:

Expected violation of operational security limits of physical transmission assets.

 

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?

The remedial actions considered in the FB DA CC process were assessed as not sufficient or ineffective to avoid the expected violation of operational security limit(s).