Capacity Curtailment on the NLL-GB-BE border for delivery period 18-11-2024

Published:

1. TSO(s)*:

Elia, NGESO

2. Identification of affected Long Term Transmission Rights:

NLL-GB-BE

3. Triggering event:

Curtailment due to Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

18-11-2024 22:00 - 23:00 675 MW

18-11-2024 23:00 - 24:00 675 MW

5. Amount of LTTR remaining after curtailment:

18-11-2024 22:00 - 23:00 558 MW

18-11-2024 23:00 - 24:00 289 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:

Expected violation of operational security limits of physical transmission assets.

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?

Reason for this curtailment is a forced outage on the cable 380.109 between the substations GEZEL380 and MAERL380.

*According to section 57.3 of the EU HAR, this field can be filled in within 24 hours after the initial publication